# Discovering the Costing Tools
 
# Discovering the Costing Tools
 
# Discovering the Quantity Take Off Tools
 
# Discovering the Quantity Take Off Tools
===Video Demo===
+
===Video Tutorial===
 
<div><youtube width="600" height="340">https://www.youtube.com/embed/lTUsC6OE01k</youtube></div>
 
<div><youtube width="600" height="340">https://www.youtube.com/embed/lTUsC6OE01k</youtube></div>
 
 
===Sample Files===
 
===Sample Files===
  
Line 17: Line 16:
 
* Option 1: Native authoring of IFC in BlenderBIM  
 
* Option 1: Native authoring of IFC in BlenderBIM  
  
[[File:Create project.png|200px|frame|center|Quick Project Setup, Schema and Data directories]]
+
You can find the command in Blender under Scene > IfcProject > Create Project
# You can find the command in Blender under Scene > IfcProject > Create Project
 
# Make sure to use IFC4, otherwise convert your IFC2x3 file to IFC4
 
  
 
* Option 2: Importing an .ifc file
 
* Option 2: Importing an .ifc file
  
[[File:Import file.png|200px|frame|center|Import Industry Foundation Classes .ifc]]
 
 
# Go to File --> Import --> Industry Foundation Classes
 
# Go to File --> Import --> Industry Foundation Classes
 
# Navigate to your .ifc file and Click Import
 
# Navigate to your .ifc file and Click Import
  
 
==Creating a Cost Schedule==
 
==Creating a Cost Schedule==
''Entity Definition'' of [https://standards.buildingsmart.org/IFC/RELEASE/IFC4/ADD1/HTML/schema/ifcsharedmgmtelements/lexical/ifccostschedule.htm IfcCostSchedule] <br>
+
''Entity Definition'' of [https://standards.buildingsmart.org/IFC/RELEASE/IFC4/ADD1/HTML/schema/ifcsharedmgmtelements/lexical/ifccostschedule.htm IfcCostSchedule]
 
''An IfcCostSchedule brings together instances of IfcCostItem either for the purpose of identifying purely cost information as in an estimate for constructions costs or for including cost information within another presentation form such as a work order.''
 
''An IfcCostSchedule brings together instances of IfcCostItem either for the purpose of identifying purely cost information as in an estimate for constructions costs or for including cost information within another presentation form such as a work order.''
  
Cost Schedules can be added under the Blender Scene Properties > IFC Cost Schedules Panel.
+
You can find the command in Blender under Scene Properties > IFC Cost Schedules Panel > "+ Add Cost Schedule".
 
 
Clicking "+ Add Cost Schedule" will add as many schedules as required.
 
 
 
 
 
  
 
===Editing attributes===
 
===Editing attributes===
Before populating our Cost Schedules with cost items, it is best to give further information about the Cost Schedules.
+
Whenever the greasepencil button is present, this enables editing the selected entity's attributes.<br>
This is done by editing the Cost Schedules attributes, by clicking on the "Grease Pencil"
 
 
 
  
 
A Cost Schedule has the following attributes you can edit:
 
A Cost Schedule has the following attributes you can edit:
Line 50: Line 40:
 
*Update Date,
 
*Update Date,
  
Note: The Cost Schedule's Predefined Type can either be chosen from the dropdown list, or set as "USERDEFINED". If the latter is set as "USERDEFINED", then the attribute Object Type should denote the particular type that further defines the object.<br>
+
The Cost Schedule's Predefined Type can either be chosen from the dropdown list, or set as "USERDEFINED". If the latter is set as "USERDEFINED", then the attribute Object Type should denote the particular type that further defines the object.<br>
  
 
===Creating Cost Items===
 
===Creating Cost Items===
''Entity Definition'' of  [https://standards.buildingsmart.org/IFC/RELEASE/IFC4/ADD1/HTML/link/ifccostitem.htm IfcCostItem]<br>
+
''Entity Definition'' of  [https://standards.buildingsmart.org/IFC/RELEASE/IFC4/ADD1/HTML/link/ifccostitem.htm IfcCostItem]
 
''An IfcCostItem describes a cost or financial value together with descriptive information that describes its context in a form that enables it to be used within a cost schedule. An IfcCostItem can be used to represent the cost of goods and services, the execution of works by a process, lifecycle cost and more.''
 
''An IfcCostItem describes a cost or financial value together with descriptive information that describes its context in a form that enables it to be used within a cost schedule. An IfcCostItem can be used to represent the cost of goods and services, the execution of works by a process, lifecycle cost and more.''
 
Refering to the figure below, and the attached template, a basic cost item structure would look like this:
 
 
[Insert Figure]
 
[Insert Template]
 
 
The parent items should contain calculations of overall quantities and/or overall costs, whilst the related nested items would contain the specific quantites and costs of assigned Building Elements, Processes, or Resources.
 
  
 
===Adding Cost Item Values===
 
===Adding Cost Item Values===

Please note that all contributions to Wiki.OSArch are considered to be released under the Creative Commons Attribution-ShareAlike (see Wiki.OSArch:Copyrights for details). If you do not want your writing to be edited mercilessly and redistributed at will, then do not submit it here.
You are also promising us that you wrote this yourself, or copied it from a public domain or similar free resource. Do not submit copyrighted work without permission!

To edit this page, please answer the question that appears below (more info):

Cancel Editing help (opens in new window)

Template used on this page: