Excavation MicroMVD
The following MicroMVD vocabulary can be used to ensure that the model captures data relevant to bulk excavation works during construction.
Feature: Excavation
In order to evaluate costs and construction sequencing of excavation work
For cost planners and construction planners
Excavation volumes must be present in 3D with relevant metadata
Scenario: Bore hole log data must be digital
* Bore hole log data must be in "{format}" format
Scenario: Bulk excavation volumes must be present
* At least one excavation volume is present.
* Excavation volumes must be uniquely named from the following list:
| Name |
| {name} |
* All excavation volumes must be assigned to a material, named from the following list of possible materials:
| Name |
| {material_name} |
* All excavation volume materials must be broken down into its constituents
* All excavation volume materials must store the material density
* All excavation volume materials must store the bulking factor as a property called BulkingFactor in a custom property set called uMVD_MaterialExcavation
You can fill out the variables using the guide below.
| Variable | Example | Description |
|---|---|---|
{format} | csv | A digital format to extract bore hole data from |